The Alstom Power Plant Laboratory Relocation project included the relocation of all industrial R&D equipment from the existing facility, to the new laboratory.  The new facility included a six story tower addition, with the scope of work including the addition of two new 23kv.208v and 23kv/480v utility services, including a new 4000 amp switchgear lineup to feed the existing relocated equipment as well as new equipment via cable tray distribution.

The project included branch power, lighting and life safety systems to include a new fire alarm system.